如何关闭持续时间自动计算 [英] How to turn off duration auto calculation

查看:159
本文介绍了如何关闭持续时间自动计算的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我正在尝试创建一个包含10个不同项目计划的高级计划计划。我在执行此操作时遇到了麻烦,因为当我将开始日期和结束日期放在不同的项目文件中时,持续时间已关闭。这是因为每个
个别项目都有指定的非工作日。这意味着我无法将它们合并到一个文件中,因为某些非工作日不适用于其他项目。现在我知道我可以创建一个自定义字段并将其命名为
而不是"duration",但这是问题所在。我将使用以下示例来演示:

I'm trying to create a high-level program plan, that incorporates 10 different project plans. I'm having trouble doing this because the durations are off when I put the start and end dates in a different project file. The reason for this is because each individual project has it's specified non-working days. This would mean that I couldn't incorporate them into a single file because some non working days aren't applicable to other projects. Now I know that I could just create a custom field and name it something other than "duration", but here's the problem with that. I'll use the following example to demonstrate:

>计划计划:34天

  >摘要任务1: 24天

  >Summary task 1: 24 days

     >子任务: 12天

     >Sub task: 12 days

     >子任务: 12天

     >Sub task: 12 days

  >摘要任务2: 10天

  >Summary task 2: 10 days

    >子任务: 5天

    >Sub task: 5 days

    >子任务: 5天

    >Sub task: 5 days

如果将这些持续时间放在自定义字段中,并且我要在摘要任务1中更改子任务的持续时间,例如,然后摘要任务1和程序计划持续时间不会改变。我确定之前有人遇到过这个问题。是否有
的解决方案?

If these durations were placed in a custom field and I were to change the duration of a sub task in summary task 1, for example, then summary task 1 and program plan durations would not change. I'm sure someone has run into this problem before. Is there a solution?

推荐答案

您是否考虑过关闭项目的计算? 项目选项>时间表>计算=关闭。 然后使用F9更新。 
Have you thought about just turning off Calculation for the project?  Project Options > Schedule > Calculation = Off.  Then use F9 to update. 


这篇关于如何关闭持续时间自动计算的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!