PS2013 CSOM如何将预算资源分配给项目摘要任务? [英] PS2013 CSOM how can I assign budget resources to the project summary task?

查看:294
本文介绍了PS2013 CSOM如何将预算资源分配给项目摘要任务?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我正在从其他系统导入项目的成本和工作估算值,我希望使用预算工作和预算成本分配,以便通过投资组合分析功能使用它们来选择项目。 我可以在Project Professional中手动执行
,但仅限于项目摘要任务。 即使预算资源已添加到项目并手动分配给项目摘要任务,CSOM也不会让我通过CSOM更新
分配的BudgetWork或BudgetCost字段。 我已经读过,摘要任务的分配通常是禁止的,但这是为项目输入预算的唯一方法,所以这是一个例外。 

I am importing cost and work estimates for a project from another system and I want to use budget work and budget cost assignments for these so they can be used by the Portfolio Analysis feature to select projects.  I can do this manually in Project Professional, but only on the Project Summary task.  Even if the budget resources are added to the project and assigned to the project summary task manually, CSOM will not let me update the BudgetWork or BudgetCost fields for the assignment via CSOM.  I have read that assignments on summary tasks are a no-no generally speaking, but that is the only way to enter a budget for a project, so this is an exception. 

我得到的错误是NullReferenceException,而不是更有意义的东西。 我已经请求了ULS日志,但还没有收到它们,我不相信它们会产生更有意义的东西。

The error that I get is a NullReferenceException, not something more meaningful.  I have requested the ULS logs but have not received them yet and I am not confident that they will yield anything more meaningful.

这可以通过CSOM或PSI完成吗? 如果是这样,秘密是什么?

Can this be done via CSOM or PSI?  If so, what is the secret?

Bruce Lofland http://blog.pmtechnix.com

Bruce Lofland http://blog.pmtechnix.com

推荐答案

查看本文,特别是有关成本资源的内容:

https://msdn.microsoft.com/en- us / library / office / ee767706.aspx

See this article, specifically the bit about Cost Resources:

https://msdn.microsoft.com/en-us/library/office/ee767706.aspx

CSOM主要利用PSI。 因此,如果PSI无法做到这一点,那么CSOM将无法做到。

CSOM basically leverages the PSI.  Hence if the PSI can't do it, CSOM won't be able to.

你基本上没有使用Project Pro(如你所见)或第三方工具UMT360。

You're basically stuck w/ Project Pro (as you've found) or third party tools like UMT360.


这篇关于PS2013 CSOM如何将预算资源分配给项目摘要任务?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!