MS Project 2010:更新项目功能;在< date>之后重新安排未完成的工作信息 [英] MS Project 2010: Update Project function; Reschedule uncompleted work after <date> message
问题描述
嗨 -
每当我尝试使用更新项目功能将未完成的工作重新安排到某个特定日期时,我会收到一条消息,指出Project没有重新安排某些未启动的工作活动因为约束日期适用于他们....
Every time I try and use the Update Project function to reschedule uncompleted work to a certain date, I receive a message stating that Project did not reschedule certain unstarted activities because of constraint date applied to them....
我的问题是:
- 是否需要删除所有约束并将其设置为As计划安排/计算到状态/数据日期的时间表是否很快?
- Do all constraints need to be removed and set to As soon as possible for the schedule to schedule/calculate to the status/data date?
- 如果我希望某些任务尽可能晚,将他们的自由浮动出去怎么办...它会计算/计划吗?
- What if I want some tasks to be As late as possible, taking their free float out...will it calculate/schedule?
- 如果我希望结束活动不晚于约束完成,如果计划延迟计划导致负浮动,该怎么办?
- What if I want the end activity to have a Finish no later than constraint, causing negative float if the schedule is planned to be late?
感谢您输入。
推荐答案
Tf0,
首先是背景:当你使用"更新项目"时要重新安排未完成的工作,Project会为未启动的工作插入SNET约束(对应于您输入的日期)。 如果您的任务已经具有非ASAP约束(除了
a SNET,其日期早于您的重新安排日期),那么Project将不会重新安排工作并将提供您引用的消息。
First the background: when you use "Update Project" to reschedule uncompleted work, Project inserts a SNET constraint (corresponding to the date you've entered) for unstarted work. If your task already has a non-ASAP constraint (other than a SNET whose date is earlier than your re-schedule date), then Project will not reschedule the work and will give the message you reference.
针对您的具体问题:
- 除了过去的SNET之外,是 - 如果您想要项目,则需要删除约束重新安排工作。 如果您的日程安排依赖于众多约束,那么您必须自己重置这些约束。
- 项目没有零自由浮动约束。 它的ALAP约束删除了一个任务的Total Slack - 不是很有用。您可以使用一些向后逻辑以及一些重复任务来模拟Project中的ZFF调度,以保留正确的逻辑
流。 - 使用截止日期代替FNLT。
顺便说一句,项目的"状态日期"和是一个比"数据日期"更弱的结构。在其他工具中。 最好不要混淆它们。
By the way, Project's "Status Date" is a much weaker construct than the "Data Date" in other tools. It's best not to confuse them.