如何更具体的微软项目的开始和结束时间 [英] How to be more specific with start and finish times in microsoft project
问题描述
我正在尝试使用开始和结束信息安排到小时。这可能吗?
I am trying to schedule down to the hour with the start and finish information. Is that possible?
推荐答案
a)yopu可以设置"时间"对于开始日期或"完成"日期,但不是两者。当您提供一个值时,项目会计算一个或另一个。
a) yopu can set the "time" for either Start Date or "finish" date, but not both. Project caluclates one or the other when you supply one value.
b) 是的,你绝对可以安排一个小时,但是手动输入开始时间或完成时间会为时间表创建约束,而你实际上并没有使用Project来做它应该做的事情(Dynamic Scheudling)。
b) Yes, you can definitely schedule down to an hour, however manually typing in the start or finish times will create constraints for the schedule and you are really not using Project for what it is supposed to do (Dynamic Scheudling).
c)如果您只是使用在线项目,请在Schedule PDP中导航到Options选项卡,然后选择Time with Date,以查看每个附加的时间。日期,并修改它们
c) If you are just using project Online, in the Schedule PDP, navigate to Options tab, and select Time with Date, to see the times attached to each of the dates, and modify them
d)如果您使用的是项目专业版,请转到文件>>选项>>一般>>日期格式并选择显示时间和日期的格式,查看每个日期附加的时间,并修改它们
d) if you are using project Pro, go to File >> Options >> General >> date format and select a format that shows time along with date, to see the times attached to each of the dates, and modify them