平衡管理项目与跟踪实际情况 [英] balancing managing the project with tracking actuals

查看:58
本文介绍了平衡管理项目与跟踪实际情况的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

是否有人开发或找到了平衡实际工作跟踪与项目管理的最佳实践?它归结为如何构建日程表以及用于输入实际值的方法。我管理了一组计费工程师和我们最近部署Project Server 2010的
,但这并不是2010年独有的 - 自20年前我开始使用MS Project以来,我一直在努力解决这个问题。

Has anyone developed or found a best practice for balancing the tracking of actual work with the managing of the project? It comes down to how one builds the schedule and the methodology they use to input actuals. I manage a group of billable engineers and we have recently deployed Project Server 2010, but this is not unique to 2010 - I have wrestled with this since I began using MS Project 20 years ago.

例如,对于升级应用程序服务器的任务,PM必须跟踪无数子任务以确保任务正确完成。虽然我们想要衡量工程师完成的时间(并与估算值进行比较),但我们可能真的只希望工程师在整个任务中输入时间,即使他们可能负责完成所有子任务。我们希望列出子任务,但我们不想让工程师负担跟踪完成像"应用软件许可证","添加到备份例程"这样的小任务所花费的确切金额
的负担,或者"配置监视"。

For instance, for the task of, say, upgrading an application server, there are a myriad of subtasks the PM must track to insure the task is completed correctly. While we want to measure the time it takes the engineer to complete (and compare to the estimate), we may really only want the engineer to input time against the tasks as a whole, even though they may be responsible for completing all of the subtasks. We want the subtasks to be listed, but we don’t want to burden the engineer with tracking the exact amount of time it took to complete a small task like "apply software license", "add to backup routine", or "configure monitoring".

理想情况下,Project / Project Server允许我们在摘要任务级别输入实际值,但事实并非如此。我曾想过在摘要任务下创建一个用于记录实际值的子任务,然后使额外的子任务二进制里程碑为0
小时工作。然而,这方面的缺点是这些不是真正的里程碑,必须从任何里程碑视图或报告中过滤掉,它们仍然会弄乱工程师的时间表。 

Ideally, Project/Project Server would allow us to input actuals at a summary task level, but it does not. I have thought of creating one subtask under the summary task to use to record actuals, and then make the additional subtasks binary milestones of 0 hours work. However, the disadvantage to this is these are not true milestones and must be filtered out of any milestone views or reports, and they still clutter up the engineer’s timesheet. 




推荐答案

在时间表设置和默认设置屏幕中,您可以启用"允许顶级时间报告"。在时间表政策部分。我相信这会让用户在汇总级别输入时间(实际上在任何级别,我认为)。
In the Timesheet Settings and Defaults screen, you can enable "Allow top-level time reporting" in the Timesheet Policies section. I believe that will let users input time at a summary level (actually at any level, I think).


这篇关于平衡管理项目与跟踪实际情况的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!