资源配置问题 [英] Resource overallocation issue

查看:61
本文介绍了资源配置问题的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我有人力资源和机器资源。每天都有8小时的可用性。

I have a human resource and a machine resource. both have a 8 hour availability per day.

我将资源分配给任务,但随后我收到人工资源,在一天内工作14小时,因为2个任务重叠。

I assign the resource to the tasks but then I receive the human resource working 14 hours in one day as 2 tasks are overlapping.

我认为练级可以纠正这个问题,但它在我的项目中没有任何意义。

I thought levelling would correct this but it does like nothing in my project.

我还想添加机器资源,因为我们只有一台机器执行某项操作任务,所以我将人力资源和机器资源添加到任务中。我再次得到重叠。

I also wanted to add a machine resource as we only have one machine performing a certain task , so I add the human resource and the machine resource to the task. Again I get overlaps.

如何做到这一点?我是MS项目的新手,但我相信这是一项非常简单的任务,我不想通过将一个任务作为另一个任务的前任来手动完成,我希望它可以通过资源可用性进行规划。

How would one do this? I am new to MS projects but I believe this is a very simple task and I don't want to do this manually by putting one task as predecessor of the other task, I want it to be planned by resource availability.

感谢你的帮助

推荐答案

据我了解你的问题。检查任务之间的链接,如果它是第一次取消链接,并单独使资源不要缩进,如果你想单独使用它们,否则他们大多添加持续时间。

As i understand your issue. Check the link between the task if it is firstly unlink them and make the resources separately do not indent any of them if you want to have them separately otherwise they mostly add the duration.

让我知道这是否对您有所帮助..

Let me know if this help you or not..

问候,

Muhammad Enam Ur Rehman

Muhammad Enam Ur Rehman

 


这篇关于资源配置问题的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!