Looking for automated way to calculate and rollup %complete of each programming resource. For example, Project would calculate all of the assigned tasks (whether the tasks were complete 100% or not), add up all of these programmers tasks and divide by the total. Right now I do this by hand but looking for an automated report from Project 2010.

提前致谢。

推荐答案

Hello Rick,

Hello Rick,

我可能误解了您的要求,但您是否看过标有列的列"工作完成百分比"在资源工作表视图中?看起来像是你原来描述的那样。

I may have misunderstood your requirement, but have you looked at the column labelled "% Work Complete" in the Resource Sheet view? It would appear to do what you've described natively.

谢谢你,b $ b Andrew

Thanks,
Andrew