MS Project 2013上是否有功能(或方法),您可以在其中找到
原因
资源是否由于休假而过载,或者是因为任务太多而没有搜索它?

Is there a feature( or a way ) on MS Project 2013, where you can find the reason whether the resource is overloaded because of vacation or just because of too much tasks, without searching for it?

推荐答案

1 。将更多任务分配给资源时会发生过度分配,这还取决于您在项目中使用的依赖项。如果它是FS它可以正常工作,但如果它是SS那么你会出现这种情况。

1. Over allocation occurs when you assign more tasks to your resource, it also depends on which dependency you are using in your project. If it is FS it works fine but if it is SS then you will this situation.

                                                 或者 

                                                  OR 

2。如果您在一周内为您的资源分配超过40小时的工作,那么您也将面临此问题。

2. If you assign more than 40 hrs work to your resource in a week then also you will face this.

要摆脱它,您需要相应地规划资源日历。

To get rid of it, you need to plan the resource calendar accordingly.

 

您可以查看"详细信息"选项,但我认为它不会显示为什么资源过度分配。

You can check the "Details" option but i don't think it will show why resource is over allocated.

在计划时,只需记住事实。

At the time of planning only you need keep the facts in mind.

 