问题描述

我正在努力解决"最佳实践"问题。对于我们公司使用PWA和Project Pro。 我们想要开始简单;为了不让工具(这是一个好工具)压倒我们并获得糟糕的说唱。  I
也希望尽可能多地留在PWA;再次将复杂性降低到开始。 这是我的斗争。 对于说40小时努力/工作的任务,我希望能够说我有3周/持续时间来完成它。 为什么&NBSP?;
如果我有3个项目正在使用这个资源,我可能在一个项目上有40个小时,在另一个项目上有40个小时,然后我在上面提到的40个小时,但是,我希望它们能够同时工作。他们 这可能吗? 我可以付出努力/工作,40美元一小时的b $ b,但说持续时间是120小时吗? 


这样,当我查看资源使用情况和可用性时,这个人将在三个不同的项目中显示3周内的充分利用。  是我要求的可能?


Cletus51

解决方案

这是非常基本的要求,而且相当可行。


在项目中将资源分配给任务,选择开始日期,结束日期。持续时间将自动计算。


因此,如果您选择3周的持续时间并将一个资源分配给任务,则总工作量将计算为120小时。


现在您希望持续时间为3周,但工作时间为40小时。只需转到工作栏并将工作时间更改为40小时。


我相信它应该对您有所帮助。



I am having a difficult time trying to settle on a "best practice" for our company with respect to using PWA and Project Pro.  We want to start out simple; so as to not allow the tool (which is a good tool) to overwhelm us and get a bad rap.  I also want to stay in PWA as much as possible; again to keep the complexity down to start with.  Here is my struggle.  On a task of say 40 hours of effort/work, I would like to be able to say I have 3 weeks/duration to complete it in.  Why?  If I have 3 projects that this resource is working on, I may have 40 hours on one project, 40 hours on another and then of course the 40 hours i mention above but, I want them to work concurrent on them.  Is this possible?  Can I put an effort/work, of 40 hours on something but say the duration is 120 hours? 

This way, when I look at the resource usage and availabilty this person will show fully utilized over the 3 week span on three different projects.  Is what I am asking for possible?


Cletus51

解决方案

That is very basic requirement and fairly possible.

In Project assign the resource to task, select start date, end date. Duration will be automatically calculated.

So if you select 3 weeks duration and assign one resource to task, total work will be calculated as 120 hours.

Now you want the duration to be 3 weeks but the work to be 40 Hours. Just go to the work column and change the work to 40 hours.

That it I believe should help you.