即使计算设置为关闭,主计划仍会计算 [英] Master Schedule Still Calculates even though Calculation is set to off

查看:63
本文介绍了即使计算设置为关闭,主计划仍会计算的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我们在单个主计划下有十几个子计划,并且在计划之间存在依赖关系。  我们已将每个计划模式设置为关闭,包括主计划。  当我们打开主计划时,它将自动计算
(我们不希望它做的事情,我们运行手动计算,因此我们可以在计算主计划之前和之后进行比较哪些依赖关系受到影响等)。  是否还有其他人遇到此问题,是否有修复方法?  我已尝试将
用于每个计划,并取消选中该框以显示计划之间的依赖关系,以查看我是否影响计算模式,但仍然自动计算。  任何帮助将不胜感激。  

We have a dozen sub schedules under a single Master Schedule with dependencies between schedules.  We have set each schedules Calculation Mode to Off, including the master schedule.  When we go to open the Master Schedule it will auto calculate (something we don't want it to do, we run manual calc so we can do a comparison of before and after the master schedule is calculated to see which dependencies are impacted etc.).  Has anyone else run into this, and is there a fix?  I've tried going to each schedule and unchecking the box to show dependencies between plans to see if that my impact the calculation mode, but it still auto calcs.  Any help would be appreciated.  

推荐答案

嗨Jedmo,

Hi Jedmo,

只是想检查计算是否必须是手动的,你不要不希望更新在主项目和子项目之间流动,然后您可以轻松地将它们作为嵌入式副本而不是链接副本插入。

Just wanted to check if the calculations have to be manual and you don't want updates to flow between Master and Sub Projects then you could have easily inserted them as embedded copy rather then a linked copy.

当您将项目插入Master时,只需取消选中该框 - "链接到项目"即可。这将使子项目成为主项目的一部分,而不是链接的实体。

When you are inserting a project into Master just un-check the box - "Link to Project" this will make sub-project as a part of Master Project rather then the linked entity.


这篇关于即使计算设置为关闭,主计划仍会计算的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!