我在项目中添加任务。我将它们链接在一起。按照我的意愿,任务按照我输入的顺序显示。然后,当我关闭并重新打开项目时,任务就被使用了。我该如何避免这种情况?

I add tasks in a project. I link them together. The tasks are shown in the order I entered them, as I wish. Then when I close and reopen the project the task are resorted. How can I avoid this?

推荐答案

听起来好像在默认视图中将排序顺序设置为日期(也许是开始)日期?)。您可以在"视图:数据"选项卡上(在Project 2010中)修复此问题,然后选择"排序"和"按ID"(或"项目" - >"在2007中排序")。保存项目。下次打开
时,任务应按照将其添加到WBS末尾的顺序。

It sounds as though in your default view you have the sort sequence set as a date (maybe start date?). You can fix this on the View:Data tab (in Project 2010) then select Sort and by ID (or Project->Sort in 2007). Save the project. Next time you open it, the tasks should be in the sequence in which you added them to the end of the WBS.