问题描述

我的项目中有很多PBI,每个PBI都有任务,其余工作都已完成.我已经完成了一些任务,其他任务尚未开始,而其他任务正在进行中.

I have on my project many PBIs and each PBI has tasks with remaining work filled in. I have finished some of my tasks, others are not started and others are in progress.

但是,燃尽图未显示任何内容.不确定我到底缺少什么配置!

However, the burndown chart is not showing anything. Not sure exactly what I am missing to configure!

我的迭代是这样的:

推荐答案

这与以下事实有关:烧毁至少需要2天的数据才能显示某些内容. 因此,基本上它不会在冲刺的第一天显示任何数据,但在第二天一切都令人惊讶地"工作.例如,在

This has to do with the fact that the burn down needs at least 2 days of data to show something. So basically it won't show any data the first day of the sprint but everything works 'surprisingly' on the second day. This is a longer existing issue as can seen for example on https://connect.microsoft.com/VisualStudio/feedback/details/788378/tfs-ervice-burndown-chart-first-day-work-did-not-get-reflected-in-burndown-chart.

在我目前的团队中,我们将使sprint的第一天(当我们进行sprint计划时)是一个团队休息日.这样可以确保第二天显示图表.在计划日直接关闭项目将降低消耗图表的起点.对于Scrum来说,这不是一个真正的问题,因为图表必须反映需要完成的工作,而不是已经完成的工作,但是对于我们的实习过程,这在过去已经引起了很多混乱.

In my current team we will just make the first day of our sprint (when we do the sprint planning) a team day off. This will make sure that the next day the chart is showing. Closing items directly on the day of planning will lower the starting point of the burn down chart. For scrum this is not a real issue because the chart must reflect the work that needs to be done and not the work that has already been done, but for our intern processes this has been causing a lot of confusion in the past.