资源的预订值始终通过在线项目更改为“建议的” [英] Resource's Booking value is always changed by project online to "Proposed"
问题描述
我正在使用2016 MSO(16.0.9226.2114)项目在线项目,每次我签出一个现有项目都要保留它我只是注意到企业资源具有建议和未承诺的预订价值。因此,我需要
来手动插入项目计划中为每个资源提交的值,然后保存,发布和签入。
I am using the project 2016 MSO (16.0.9226.2114) with project online and each time I check-out an existent project do maintain it I just notice that the enterprise-resources have the booking value with proposed and not committed. Because of that, I need to manually insert the value committed for each resource in the project plan, then save, publish and check-in.
如果我不这样做上述步骤,企业资源将在相应的时间表中丢失项目的任务,我们正在使用在线项目来监控资源。
If I do not do the above steps, the enterprise resource will lose the project's tasks in the the respective time-sheet and we are using the project online to have the resources effort monitor and control.
我想设置设置在线项目不会弄乱预订值的方式。你知道吗?
I would like to setup the settings in a way that the project online does not mess up the booking values. Do you know how ?
谢谢和问候
Carlos
推荐答案
Carlos - 您可以设置"预订类型"。对于来自"从企业构建团队"的项目团队中的资源对话框(方便提示 - 使用CTRL + T键盘快捷键),这将建立主流类型,建议或为整个项目提交
。
Carlos - you can set the "booking type" for Resources in your project team from the "Build Team from Enterprise" dialog box (handy hint - use the CTRL+T keyboard shortcut), this establishes the prevailing type, either proposed or committed for the entire project.
我怀疑您的每个任务的编辑可能会因为它们与值的冲突而被丢弃 在"从企业构建团队"中可见对话框。
I suspect that your edits per task may be discarded as a result of them conflicting with the values visible in the "Build Team from Enterprise" dialog box.
尝试我的建议,看看你是如何继续的。
Try my suggestion and see how you get on.
这篇关于资源的预订值始终通过在线项目更改为“建议的”的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!