固定工作和固定持续时间 [英] Fixed Work and Fixed Duration

查看:83
本文介绍了固定工作和固定持续时间的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好,


我是建筑项目规划师,长期以来一直使用Microsoft Project,主要是没有Primavera的承包商(另一个规划工具) )


我首选的工具是Primavera,因为它允许您拥有同时具有固定工作和固定持续时间的任务。我需要这个功能,因为我有固定的预算时间,我想通过手动更改持续时间而不用
项目自动更改我的预算来分散这些时间。这是我与之交谈的很多用户都遇到的问题。


据我所知,Microsoft Project中没有解决方案。 MS Project允许您使用"固定工作"执行任务但更改"工作"时更改持续时间,或者您可以使用"固定持续时间"但更改持续时间时更改工作。
 我不希望这些行为发生。


我搜索了这些论坛,但没有找到解决方法或宏。有没有人见过这个解决方案?


干杯,

Max

解决方案

Max,


就具有两个固定参数而言,Project的基础工作方程(持续时间=工作/单位)不支持它。但是,使用固定工作类型任务时,您声明能够更改持续时间并使工作保持固定的愿望很容易。这允许
你改变持续时间,Project会自动在新的持续时间内重新分配固定的工作内容。显然资源分配水平也会发生变化。


这是否符合您的需求?


John


Hello,

I am a construction project planner and have used Microsoft Project on and off for a long time mainly with contractors that don't have Primavera (another planning tool)

My preferred tool is Primavera because it allows you to have a task that has both Fixed Work and a Fixed Duration. I need this functionality as I have fixed budgeted hours and I want to spread those hours over time by manually changing the duration without Project automatically changing my budget. This is a problem that a lot of users I talk to have with Microsoft Project.

As far as I am aware there is no solution to this in Microsoft Project. MS Project allows you to have a task with Fixed Work but that changes the duration when you change Work, or you can have Fixed Duration but that changes the work when you change duration.  I don't want either of these behaviours to happen.

I have searched these forums but have not found a workaround or macro. Has anyone seen a solution to this?

Cheers,
Max

解决方案

Max,

As far as having two fixed parameters, Project's underlying work equation (Duration = Work/Units) doesn't support it. However, your stated desire to be able to change the duration and have the work remain fixed is easy with a Fixed Work type task. That allows you to change the duration and Project will automatically re-spread the fixed work content over the new duration. Obviously the resource assignment level will also change.

Does this not meet your needs?

John