如果剩余工作更改为“0小时”,则完成百分比不会更新如果是固定持续时间。 [英] %Complete is not updating , if remaining work changes to "0hrs" if it is a Fixed Duration.

查看:115
本文介绍了如果剩余工作更改为“0小时”,则完成百分比不会更新如果是固定持续时间。的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

 


我在项目计划中创建了一个任务,并将任务类型指定为"固定持续时间"。 


任务详情: 



  • 任务名称:
    任务测试: 
  • 任务类型:
    固定持续时间  
  • 任务工作: 10小时( 10天) 
  • 任务开始日期: 04 -mar-2013 
  • 任务完成日期: 15 -Mar-2013 

我在时间表中提交了此任务的实际工时是"1小时"。并批准同样的。 


之后我打开了计划并将剩下的工作做成了"0小时"。然后它显示"%work Complete" 100%和%完成为"10%" 如果剩余的工作变为"0小时",则为
然后它必须显示"100%"(因为没有剩余的工作)。 


能否帮我解决一下如何解决这个问题?


非常感谢提前...... !!!


谢谢


< p style ="line-height:18pt"> venkat。

解决方案

将任务类型更改为固定单位或固定工作



设置剩余持续时间到0



%完成字段显示% Duration 完成。 &NBSP;您的任务计划为持续10天的10小时任务。 当您报告实际工时为1小时时,项目推断出您在任务的第一天(1小时)工作了
。 因此,工作和持续时间都设定为10%。 当您将剩余工作设置为0时,项目正确地将%Work Complete设置为100%,但将%Complete保留为10%,因为固定
持续时间任务中仍有9天剩余时间。


Hi, 

I have created one task in the project plan, and given the task type as "Fixed Duration". 

Task Details: 

  • Task name: Task Test: 
  • Task Type: Fixed Duration 
  • Task Work : 10hrs (10 days) 
  • Task Start Date: 04-Mar-2013 
  • Task Finish Date: 15-Mar-2013 

I have submitted Actual work for this task in the time sheet is "1hr" and approved the same. 

After that I have opened the plan and made the remaining work to "0hrs". Then it is showing "%work Complete" as 100% and %Complete as "10%"  if the remaining work becomes to "0hrs" then it has to be display "100%"(Since there is no remaining work). 

Could you please help me on how to resolve this issue?

Many thanks in advance...!!!

Thanks

venkat.

解决方案

Change the task type to Fixed Units or Fixed Work

OR

Set Remaining duration to 0

The % complete field displays the % Duration complete.  Your task was planned as a 10-hour task over 10 days duration.  When you reported Actual Work of 1 hour, project deduced that you had worked the first (1-hour) day of the task.  Therefore both work and duration were set to 10%.  When you set remaining work to 0, project correctly set % Work Complete to 100%, but left % Complete at 10% because there were still 9 days remaining in the Fixed Duration task.