剩余工作和持续时间为0,但完成百分比保持在99% [英] Remaining Work and Duration is 0, but % Complete stays at 99%

查看:257
本文介绍了剩余工作和持续时间为0,但完成百分比保持在99%的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好,

任务的剩余工时为0小时,同一任务的剩余持续时间为0天。完成百分比和工作完成百分比字段不会重新计算为100%,但保持在某个值以下(例如99%)。

Remaining work on a task is 0 hours, and Remaining duration for the same task is 0 days. The % Complete and % Work Complete fields do not re-calculate to 100%, but stay at some value below (e.g. 99%).

任务类型是固定单位,没有努力驱动,自动安排,并且没有约束类型(尽快开始)。

Task Type is Fixed Units, Not Effort Driven, Automatically scheduled, and there are no constraint types (Start As Soon As Possible).

我无法将%Complete编辑为100%,因为我们的项目服务器配置只允许PWA上的时间表更新任务。

I cannot edit the % Complete to 100% because of our project server configuration to only allow task updates from timesheets on PWA.

如何正确更新任务以获得完成百分比到100%?

How do I update the task correctly to get % Complete to 100%?

见下面的截图。

推荐答案

shaundicker -

shaundicker --

资源是否在问题实际上在他/她的时间表页面或PWA中的任务页面上有关于此任务的一些剩余工作? 如果是这样,请让他/她将剩余工作设置为0h,然后提交任务更新。

Does the resource in question actually have some Remaining Work on this task on his/her Timesheet page or Tasks page in PWA?  If so, ask him/her to set Remaining Work to 0h and then submit the task update.

除了上述内容之外,我还在Microsoft Project 2013中看到过这种行为。  ;这是您正在使用的软件版本吗? 顺便说一句,你从来没有告诉我们,如果我们知道的话,它会有所帮助。 无论如何,通过按F9功能键强制重新计算项目,我能够解决
问题。

In addition to the above, I have also seen this behavior myself in Microsoft Project 2013.  Is that the version of the software you are using?  You never told us, by the way, and it would help if we knew.  Anyway, I was able to work around the issue by pressing the F9 function key to force a recalculation of the project.

此外,无论您使用何种版本的软件,我强烈建议您确保将最新的Service Pack和累积更新应用于SharePoint,Project Server和Microsoft Project Professional的每个副本。 
希望这会有所帮助。

In addition, whatever version of the software you are using, I would strongly recommend that you make sure that you have the latest Service Packs and Cumulative Updates applied to SharePoint, Project Server, and each copy of Microsoft Project Professional.  Hope this helps.


这篇关于剩余工作和持续时间为0,但完成百分比保持在99%的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!