问题描述

嗨!我真的想从完成日期向后计划,以便在理论上看到该项目中的不同里程碑应该最迟完成。但是我得到了所有这些奇怪的依赖,这些依赖并不像我期望的那样工作。当然,我主要使用
ALAP约束我的任务。主要观察是,即使我尝试定义所有任务导致的早期完成里程碑,该计划的行为就像项目完成日期是所有任务的完成日期一样。但是我可以忍受这一点,更有意思的是,很多任务根据他们的依赖关系不愿意及时滑出 - 他们有时会在没有任何明显原因的情况下及早陷入困境。有没有基本的我忘记定义或MS Project无法做到这一点?

Hi! I would really like to plan backwards from a Finish Date to see theoretically when different milestones in the proejct should be finished at latest. But I get all these weird dependencies that are not working the way I expect. I mainly use, of course, ALAP constraint on my tasks. The main observation is that the plan act as if Project Finish Date is the Finish Date of all tasks even if I try to define an earlier Finish Milestone that all tasks lead up to. But this I can live with, What's more wired is that a lot of tasks are not willing to slide out in time according to their dependencies - they are kind of stuck earlier in time without any obvious reason. Is there something fundamental I have forgot to define or is MS Project not able to do this?

推荐答案

嗨Arild,

Hi Arild,

我没有花时间编写所有的方法论,而是更喜欢给你一个关于MVP Tim Runcie的后向调度的优秀参考:

Instead of spending time to write all the methodology, I prefer giving you this excellent reference about backward scheduling by a fellow MVP Tim Runcie:

http:/ /blog.advisicon.com/2015/06/30/how-to-reverse-engineer-a-microsoft-project-schedule /

告诉我们如果它有帮助。

Tell us if it helps.


这篇关于项目中的后向规划的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!