问题描述

您好,


在我们的每周跟踪周期中,我们要求我们的资源报告2个字段:


  1. 实际工作
  2. 剩余工作

我们不想使用MSP的自动计算(剩余工作=以前的剩余工作 - 实际工作) ,但希望剩余的工作保持其以前的状态,并让资源手动更新剩余的工作。


否则,当资源报告的次数超过计划的工作时,我们会自动关闭活动。 / p>

有没有办法以这种方式配置MSP?


谢谢,


Yuval


解决方案

在分配级别进行更新时;如果输入大于工作的实际工时,则项目将工作设置为实际工作,剩余工作设置为零(如果您未输入剩余工作!)并根据$ b $完成工作分配(%工作完成= 100%) b关于公式工作=实际工作+剩余工作。没有设置可阻止Project更新"剩余工时"字段。


当所有作业完成后,任务级别的%Work Complete和%Complete将为100%。虽然我不明白为什么你不能获得剩余工作的估计以及实际工作的原因,但我建议你取消勾选
选项"更新任务状态更新资源状态"。在"项目选项"对话框的"计划"选项卡中。因此,即使%Work Complete显示100%,在更新实际工作时,任务级别的%Complete也不会更改。

















$


Hi,

in our weekly tracking cycle we ask our resources to report on 2 fields:

  1. Actual Work
  2. Remaining Work

we do not want to use the automatic calculation by MSP (Remaining Work = Previous Remaining Work - Actual Work), but would like the remaining work to keep it's previous status and have the resources manually update the remaining work.

otherwise we experience activities closed automatically when the resource reports more then the planned work.

Is there a way to configure MSP in such way?

Thank you,

Yuval

解决方案

While updating at the assignment level; if you enter Actual Work which is greater than Work, then Project sets Work to Actual Work, and Remaining Work to zero (if you do not enter remaining work!) and completes the assignment (% Work Complete = 100%) based on the formula Work = Actual Work + Remaining Work. There is no setting to prevent Project from updating the Remaining Work field.

When all the assignment are complete, both %Work Complete and % Complete at the task level will be 100%. Although I do not understand the reason why you cannot obtain estimates on the remaining work along with the actual work, I would suggest you to uncheck the option "Updating Task status updates resource status" in the Schedule tab of the Project Options dialog box. Thus, % Complete at the task level will not change while you update the actual work even when % Work Complete shows 100 percent.