查看:91
本文介绍了特定资源的非工作时间的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我已经回顾了建议的答案,但它们似乎不适合我的情况。   Project 2013 Pro。

I have reviewed the suggested answers and they don't seem to fit my case.   Project 2013 Pro.

我有一个特殊的资源需要休息三天。这些天发生在8天任务的中间,固定的持续时间,他只工作20%。他有自己的日历来提供这些信息,我已经检查了那个人在资源
工作表/资源信息中显示的日期。   Gantt视图中的酒吧没有显示他起飞三天的事实。 (标准时间关闭设置为'在任务栏后面')。 

I have a particular resource who takes three days off. These days occur in the middle of an 8 day task, fixed duration, on which he is only working 20%. He has his own calendar to deliver this information and I have checked that the days off display in Resource Sheet/Resource Information  for that person.  The fact that he takes off three days is not shown by the bar in Gantt view. (standard time off is set to 'behind task bars'). 

如果我暂时将其承诺更改为100%,则任务表中的计算小时数为40,表明软件识别他的休息时间,否则它将是8x8 = 64。他工作时间的差距仍然没有表现出来。  

If I temporarily change his commitment to 100%, the calculated hours in the task form are 40, showing that the software is recognising his time off, since otherwise it would be 8x8=64. The gap in his work time still doesn't show.  

有没有办法显示差距,以便我知道(好吧,记住)这三天他不在身边?

Is there a way to show the gap so that I know (well, remember) he is not around for those three days?

干杯

Alan 

Alan 

推荐答案

TeamPlanner视图显示资源的非工作时间,如下所示: 

TeamPlanner view shows the resource's nonworking time as it is seen below: 


这篇关于特定资源的非工作时间的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!