i have task has submitted and saved hours, and i need to extract only submitted hours
i will give you an example:
if i submit 10 hours on task(task_ID=xxxx) and put another 10 hours and press save, i need to display table as below:
Task Hours
xxxx 10
so, i need to find something that differentiate between submitted hours and saved hours per task, does the project server contain any status to differentiate between the submitted and saved hours.
Hi Mohammed,
this is a bit difficult to achieve without development.
The data is only available from the published database (or pub. tables in 2013).
You can try to use MSP_ASSIGNMENTS_SAVED and MSP_ASSIGNMENTS_PUBLISHED tables for that.
But this procedure is not supported.
Kind regards
Christoph