问题描述

您好,

我目前正在尝试在MS Project中创建包含许多重复任务的月度任务列表。大多数任务都与会计时间表相关联,这些会计时间表集中在我们月末,即工作日10,工作日-4等每月

I am currently trying to create a monthly task list in MS Project which contains a number of recurring tasks. The majority of the tasks are associated with an accounting timetable focussed around our month end i.e. working day 10, working day -4 etc. of each month.

有没有办法我可以修改日历来计算每个月的工作日,以便正确安排任务吗?

Is there any way I can amend the calendar to calculate working days for each month so that the tasks are scheduled correctly?

提前致谢。

Daniel

推荐答案

Daniel,

Daniel,

我不明白你的"工作日10,工作日-4等"。一个例子可以帮助很多。

I don't understand your "working day 10, working day -4, etc.". An example would help a lot.

当你说"修改日历以计算每个月的工作日"时,你究竟是什么意思? 

When you say, "amend the calendar to calculate working days for each month", what exactly do you mean? 

项目的工作日日历可以自定义,以提供自定义工作周,自定义工作时间和非工作日(例如假期),但无法自定义创建会计月份日历(例如4-4-5)序列)。注意:我不使用Project
Server但我知道它可以创建会计月报告。

Project's working day calendars can be customized to provide for custom work weeks, custom working hours, and non-working days (e.g. holidays), but they cannot be customized to create accounting month calendars (e.g. 4-4-5 sequence). Note: I do not use Project Server but I understand that it can create accounting month reports.

任务持续时间可以输入为日历天(例如7ed)和额外持续时间字段可以使用公式进行自定义,以提供与"持续时间"字段不同的持续时间信息。并且为了获得最大的灵活性,VBA可用于创建所需的任何
日历,但可能需要将时间刻度导出到另一个应用程序(例如Excel),以便根据需要进行查看。

Task duration can be entered as calendar days (e.g. 7ed) and extra duration fields can be customized with a formula to provide duration information different from that of the Duration field. And for the greatest flexibility VBA can be used to create whatever calendar is desired, although it may require that timescale to be exported to another application (e.g. Excel), for viewing as desired.

John