将开始日期标记为里程碑 [英] mark start date as a Milestone
问题描述
我有一个包含以下任务的模板:
I have a template with the following tasks:
准备好Qual,持续时间= 0(RFQ)
Ready for Qual, duration=0 (RFQ)
质量执行,持续时间> 0(质量开始)
Qual execution, duration>0 (Start of Qual)
质量结束,持续时间= 0 (质量结束)
End of Qual, duration=0 (End of Qual)
我想提出以下里程碑:
RFQ,Qual of Qual,Qual of。
RFQ, Start of Qual, End of Qual.
有没有办法将里程碑作为任务的开始?
Is there a way to present milestone as the start of a task?
Thx,Yael。
推荐答案
Yael,
我对您的请求感到有些困惑。根据定义,持续时间为零的任务是一个里程碑,看起来你就是这样。如果你要求在同一个任务上有里程碑和非零持续时间甘特条,那么一个里程碑和一个性能
任务是两个根本不同的概念。您可以修改甘特图栏以显示钻石作为条形图的开头,但这不会使其成为里程碑。
I'm a little confused by your request. By definition a task with zero duration is a milestone and it looks like you have that. If you are asking to have a milestone and a non-zero duration Gantt bar on the same task then no, a milestone and a performance task are two fundamentally different concepts. You could modify the Gantt Bar to show a diamond as the start of a bar style but that won't make it a milestone.
显示您想要的内容的正确方法是具有单独的里程碑任务作为正常执行任务的前身。在你的例子中,我将在RFQ(0持续时间)设置一个里程碑,使其成为qual执行的前任(非零
持续时间),最后使那个前身到qual(0持续时间)结束。
The correct way to show what you appear to want is to have separate milestone tasks as predecessors to a normal performance tasks. In your example I would set a milestone at the RFQ (0 duration), make that the predecessor to the qual execution (non-zero duration), and finally make that the predecessor to the end of qual (0 duration).
希望这会有所帮助。
John