[b]Hi All,

I have Resources working for us 8 hours a day as for day to day job but they have free times as well.
I want to assign tasks to them outside of their day to day job. So after I asked them how much time you can offer to me after you finished your day to day job to allocate that time for working on a project I got the following answers:

Resource1=2 hours a day
Resource2=1 hours a day
Resource3=0.5 hours a day
Resource4=1 hours a day
... and so on

Now how can I set this up on MS project 2010. I know you can play around the availability of a resource on a specific task as percentage to extend the total task time. But what I want to do, is pre-setup my resource before hand which means he/she cannot offer more than 2 hours a day. So when I assign him/her a task I want to be able to assign the number of hours that a task needs to be done and MS Project automatically looks at the time that each resources can offer and calculate the number of days which allocated resource needs to finish the task. 

hope make sense

Cheers

Ali[/b]

推荐答案

阿里,

您可以使用"最大单位数"字段设置每个资源的可用性。设置资源时(在资源工作表中)设置最大单位。 如果资源可以工作8小时,那么将最大单位设置为100%,4小时设置为50%,2小时设置为25%,依此类推。

You can use Max Units field to set availability of each resources. While setting up resources (in resource Sheet) set the Max Units.  If resource is available to work 8 hours then set max units to 100%, for 4hrs set 50% and 2 hrs set 25% and so on.

谢谢,

Kiran K。