JIRA设置-项目约束,因此需要先完成任务,然后才能开始下一组任务 [英] JIRA setup - project constraints so that tasks need to be completed before next set of tasks can begin
问题描述
如何在JIRA项目中添加业务逻辑,您可以在仅完成较早阶段的情况下继续进行下一个阶段.
How do I add the business logic in a JIRA project where you can proceed to the next stage on only completing the earlier stages.
我知道JIRA是敏捷Scrum团队的工具,因此它固有地在打破基本的敏捷原则.但是,我试图定义一个看板工作流,在该工作流中,需要先完成一组任务,然后才能开始下一组任务.我想在我的JIRA董事会中实施此业务规则.
I am aware that JIRA is a Agile scrum team tool, so it inherently is breaking fundamental agile principles. However, I am trying to define a Kanban workflow where a set of tasks needs to be completed before the next set of tasks can begin. I want to implement this business rule in my JIRA board.
推荐答案
这可能不是理想的解决方案,但是一种方法是使用子任务.
This may not be the ideal solution, but one approach is to use sub-tasks.
可以添加条件,以便除非已完成所有子任务,否则问题无法转移.
It is possible to add a condition so that an issue cannot be transitioned unless all it's sub-tasks are completed.
这篇关于JIRA设置-项目约束,因此需要先完成任务,然后才能开始下一组任务的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!