团队速度 [英] Team Velocity
问题描述
如何在TFS中计算Velocity?
How is Velocity calculated in TFS?
推荐答案
您好Jacqueline Giammanco,
Hi Jacqueline Giammanco,
感谢您在此发帖。
您的意思是Velocity图表吗?该图表跟踪您的团队在之前的冲刺中完成(绿色)或仍在进行中的预计积压工作(努力,故事点或大小的总和)(蓝色)。
Did you mean the Velocity chart? The chart tracks your estimated backlog work (sum of Effort, Story Points, or Size) that your team has completed (green) in the previous sprints, or that are still in progress (blue).
例如,在Scrum模板中,绿色数字表示PBI在冲刺中完成状态的总工作量,然后蓝色数字表示PBI的总工作量冲刺中的承诺状态。有关详细信息,请参阅以下
链接:
https://www.visualstudio.com/en-us/docs/work/scrum/velocity-and-forecasting
For example, in Scrum template, the green number means the total effort of PBI in Done State in a sprint, then blue number means the total effort of PBI in Committed State in a sprint. For detailed information, you could refer to the following
link:
https://www.visualstudio.com/en-us/docs/work/scrum/velocity-and-forecasting