project server 2010:版本化项目计划 [英] project server 2010: versioning project schedules
问题描述
您好,
是否可以在EPM中为项目计划创建某种版本控制?我感兴趣的是每当有人改变项目进度表(计划)并保存新计划时跟踪更改。每当按下保存或发布按钮时,是否可以为项目创建不同的
版本?我不想使用基线,因为基线并没有真正做我想做的事。
Is it possible to creating some kind of versioning for project plans in EPM? What I am interested in is tracking the changes whenever someone changes something on the project schedule (plan) and saves the new schedule. Is it possible to create a different version for the project whenever the save or publish button is pressed? I do not want to use baselines since baselines do not really do what I am trying to do.
最好的问候,
George
Best regards,
George
推荐答案
嗨乔治
没有优雅的方法来实现这一目标。您可以尝试在本地保存文件,然后使用Project 标签下的
比较项目功能。
There is no elegant way of achieving this. You can try saving your file locally and then use the Compare Projects function available under the Project tab.
Also try refering to a similar post: http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/a4326c16-1a3c-4abe-a782-91517ed33b83
谢谢
Meeta
Meeta