我有数据清单
list proj_name = {A,B,C,D,E,F}
列表持续时间= {6,10,5,4,9,2}
list faster_duration = {6,8,4,1,7,1}
list cost = { - ,500,300,700,600,800}
如果关键路径是ABF和CDEF
i知道我们可以使用intersec来找到相同的proj_name但是如果有超过2个关键路径知道如何找到它就不能使用吗?
每天的费用是1150
i got lists of data
list proj_name = { A,B,C,D,E,F}
list duration = { 6,10,5,4,9,2}
list fastest_duration = {6,8,4,1,7,1}
list cost = {-,500,300,700,600,800}
if critical path was A-B-F and C-D-E-F
i know that we can use intersec to find the same proj_name but it can't be use if there was more than 2 Critical path any know how to find it ?
the cost per day was 1150