问题描述

您好, 

我使用的是MP Professional(桌面版,2019)。我不是MP的新手,但是我们的公司开始使用MP的更多工具(在过去,我们保持非常简单,但随着我们的成长 - 需要更深入)。 

I am using MP Professional (Desktop version, 2019). I am not new to MP, but our company is starting to utilize more tools of MP (in the past, we have kept it very simple but as we grow - need to get more in depth). 

我有一个项目有一个截止日期(因为它有助于在日期过去时看到自动收报机)和一个完成 - 不迟于约束我们的最终发货日期。我们的资源过度分配,我们的项目已超过此截止日期/约束
天。我想知道如何确定需要做什么才能满足截止日期以及为什么MP在设定为约束时超过截止日期? 

I have a Project that has a deadline (because it is helpful to see the ticker when the date goes past) and a Finish-No-Later than constraint on our final ship date. Our resources are over-allocated, and our Project has went past this deadline/constraint day. I would like to know how to determine what needs to be done in order to meet that deadline day and why MP is exceeding the due date when it is set as a constraint? 

我们在一个资源池中有多个项目/作业,因此添加资源并不是一件简单的事情(因为,我可能在同一周内在不同的工作(项目)上过度分配,而无需手动添加资源并不断检查
新船/完工日期,我无法清楚地了解如何修改我的时间表以满足截止日期。如果约束日期已经举行,这将更容易操纵。 

We have multiple projects/jobs within one resource pool, so it is not a simple matter of adding resources (because, I might be over-allocated in the same week on different jobs (projects) that without manually adding resources and continually checking the new ship/finish date, I am unable to get a clear picture on how to revise my schedule to meet the deadline. If the constraint date was held, this would be much easier to manipulate. 

我原本预计MP会维持约束,但会显示我们可以添加资源的高度分配,因为该日期已经保留,并且需要添加资源来保持该日期。 

I would have expected MP to maintain the constraint, but show high overallocations in which we could add resources because that date is held and adding resources is what is needed to keep that date. 

对此有任何见解将不胜感激。 

Any insight on this would be appreciated. 

推荐答案

Amber2000 -

Amber2000 --

我愿意怀疑在"项目选项"对话框中已更改了一个重要选项。 单击"文件"选项卡,然后单击"后台"中的"选项"选项卡。 在"项目选项"对话框中,单击"计划"选项卡。 向下滚动到Scheduling
此项目的选项部分,然后选择名为Tasks的选项将始终尊重他们的约束日期。 单击"确定"按钮。

I would suspect that an important option has been changed in the Project Options dialog.  Click the File tab and then click the Options tab in the Backstage.  In the Project Options dialog, click the Schedule tab.  Scroll down to the Scheduling Options for This Project section and SELECT the option named Tasks Will Always Honor Their Constraint Dates.  Click the OK button.

取消选择上述选项后,Microsoft Project将根据与前任任务的任务依赖关系,允许约束任务滑过其约束日期。 选择该选项后,软件会强制执行约束
,并且不允许任务滑过约束日期。 如果有帮助,请告诉我们。

When the preceding option is deselected, Microsoft Project allows the constrained task to slip past its constraint date, based on task dependency relationships with Predecessor tasks.  When the option is selected, the software enforces the constraint and will not allow the task to slip past its constraint date.  Please let us know if this helps.