问题描述

我有一个项目计划,我直接添加了资源,现在我们正在将项目转移到在线项目,我已经从Enterprise Resource添加了资源。现在在我的PM中也获得了手动添加的资源名称。

I have a Project Plan where i have directly added resources, now we are moving our project to project online where i have added resources from Enterprise Resource. Now in my PM also getting resources name which were added manually.

有没有办法删除手动添加的资源。

Is there any way to remove manually added resources.

谢谢。

iffi

推荐答案

删除"本地资源" - 不在企业资源库中的资源,您可以考虑从资源表中删除它们。

To remove "local Resources" - resources that do not reside in the Enterprise Resource Pool you could consider simply deleting them from the Resource Sheet.

如果您希望替换"本地资源",使用命名的企业资源我建议使用企业对话框中的构建团队( CTRL + T ),您可以在其中使用企业资源替换本地资源(此方法的
优势是如果你有一个资源分配给多个任务使用这个对话框替换它们是单个事务,例如用Sam(企业资源)替换Bob(本地资源处理12个任务)是单个动作
并且每个在12个任务中,Sam现在是替代Bob的资源。

If you wish to replace "local resources" with named Enterprise Resources I would suggest using either the Build Team from Enterprise Dialog Box (CTRL+T) where you can replace a local resource with an Enterprise Resource (the benefit of this approach is that if you have a resource assigned to multiple tasks replacing them using this dialog box is a single transaction, for example replace Bob (local resource working on 12 tasks) with Sam (Enterprise Resource) is a single action and on each of the 12 tasks Sam is now the resource in place of Bob.

或者,您可以使用"分配资源"对话框( ALT + F10 )替换资源逐个任务。

Alternatively you can use the Assign Resource dialog box (ALT+F10)to replace resources on a task by task basis.

如果您已记录任务进度,则在尝试替换已记录"实际工作"的任务上的资源时可能会遇到问题。这可能是均匀的如果您碰巧使用"受保护的实际值",则会出现更多问题。

If you have recorded any progress on tasks you may encounter issues in trying to replace resources on tasks where "Actual Work" has been recorded. This can be even more of a problem if you happen to be using "Protected Actuals".