您好,

我有一个基准资源,每天工作4小时,一周最多20小时。

I have baseline a resource to work 4 hours per day, to a maximum of 20 hours for the week.

我不希望资源每天能够记录超过4小时。

I do not want the resource to be able to log any more than 4 hours per day.

似乎资源可以按照他们想要的每天工作多少小时,只要他们被分配到任务。

Is seems that resources can work as many hours per day as they want, as long as they are assigned to the task.

是这样吗?

谢谢

杰夫

推荐答案

Jeff,

Project Server将允许资源记录超过分配的工作量。但是,如果您想控制它,您可以考虑以下过程,假设您的PWA实例配置为单一输入模式,并且您定义了每周时间表时段:

Project Server will allow resources to log effort more than allocated. But if you would like to control it you can consider the following process assuming your PWA instance is configured in Single entry mode and you have weekly timesheet periods defined:

1。一旦时间表由任务超过20小时/周的资源提交,任务更新将在批准时间表后发送到状态管理器以供批准。

1. Once the timesheet is submitted by the resource which has more than 20 hrs/week on the task, the task update will be sent to the status Manager for approval after Timesheet is approved.

2。状态管理员可以查看任务更新(工作时间超过20小时)并可以拒绝任务更新。

2. The status manager can review the task update (effort greater than 20 hrs ) and can reject the task update.

3。由于状态管理器拒绝任务更新,任务的实际小时数不会反映在项目计划中。

3. As the status manager rejects the task update, the actual hours for the task will not reflect in the project plan.

4。此过程将强制资源调用并重新提交超过20小时的时间表。因为状态管理器拒绝任务更新后,时间表行的状态将在时间表中显示为已拒绝。

4. This process will enforce the resource to recall and resubmit the timesheet which was greater than 20 hrs. Because once the task update is rejected by the status manager, the timesheet line's status will show as rejected in the timesheet.

如果有帮助,请告诉我。

Let me know if this helps.

问候,

Sudhir