我的IT PMO团队已经为我们的内部IT项目实施了Project Online。我们现在有一个承包商,他将为我们开发/实施一些IT系统。我希望那个承包商也能利用Project Online,这样我就可以在一个地方拥有我所有组织的
IT项目,我可以在项目中心查看所有这些项目,包括报告。 当供应商访问项目中心时,我希望他们只能看到他们的项目,而不是我组织的所有项目。 并且,
我希望他们能够运行投资组合报告,但仅限于他们的项目。

My IT PMO team has implemented Project Online for our internal IT projects. We now have a contractor who's going to be developing/implementing a few IT systems for us. I'd like that contractor to also utilize Project Online, so that I have all of my organization's IT projects in one place, and I can view all of them as portfolio in Project Center, including reports.  When the vendor accesses Project Center, I want them to only be able to see their projects, not all of my organization's projects.  And, I want them to be able to run portfolio reports, but just on their projects.

最好的方法是什么? 给承包商"投资组合经理"或"投资组合查看器"导致他们看到所有项目,所有风险/问题,延迟任务和其他项目被纳入投资组合报告。 

What's the best approach for this?  Giving the contractor "Portfolio Manager" or "Portfolio Viewer" results in them seeing all projects, and all risks/issues, late tasks, and other items being pulled into portfolio reports. 

我应该创建Project Online的单独实例吗? 或者,是否有一种创建单独的"投资组合管理器 - 承包商"的好方法。限制他们可以看到哪些项目的权限?

Should I create a separate instances of Project Online?  Or, is there a good way to create a separate "Portfolio Manager - Contractor" permission that limits which projects they can see?

推荐答案

听起来安全组"项目经理"是您的承包商的正确选择。项目经理默认只看到自己的项目。报告可以通过/ projectserver feed完成,它考虑了相应的
角色的权限。它主要由开发人员使用。在这里你可以找到一个文档:https://msdn.microsoft.com/en-us/library/office/jj712612.aspx?f = 255&MSPPError = -2147217396使用/ projectdata feed报告要容易得多,因为像项目这样的表,任务,作业包括
。不幸的是,这是一个全有或全无的决定,所以这对你来说不合适。
Hi, sounds like the security group „project manager" is the right one for your contractor. Project Managers do only see their own projects by default. Reporting could be done by the /projectserver feed, which considers the permissions of the respective role. It is mainly used by developers. Here you can find a documentation: https://msdn.microsoft.com/en-us/library/office/jj712612.aspx?f=255&MSPPError=-2147217396 With the /projectdata feed reporting is much easier, because tables like projects, tasks, assignments is included. Unfortunately it is an all or nothing decision, so that‘s not the right thing for you.