峰值单位 [英] Peak units
问题描述
您好,
请在以下示例中说明Project如何计算峰值:
1。已修复的单位任务1持续时间为2.5天。资源John以100%分配。工作日是默认的8小时。
为什么Project计算第3天的峰值 100%如果John当天只工作4小时,那么他的能力是
50%?
2。如果在上面的示例中我们手动更改 第3天工作时间从4h到8h,即使8h / d为100%,Project也会将Peak重新计算为200%。为什么会这样做?
这是否意味着Project这样想:
第3天的持续时间为0.5d,因此当天的单位(峰值)=工作/持续时间= 4h / 05d =第一种情况为100%,第二种情况为8h / 0.5d = 200%?
谢谢,
Alex
Alex,
我无法重现此行为。你能尝试一个空白的新文件吗?您还有哪个项目版本?是否升级到最新的补丁级别?
Hello,
Please explain how Project calculates the Peak in the following examples:
1. Fixed units Task1 duration is 2.5 days. Resource John is assigned at 100% . Work day is a default 8h.
Why does Project calculate Peak for day 3 as 100% if John works only 4h on that day which is 50% of his capacity?
2. If in the example above we manually change the work for day 3 from 4h to 8h, Project recalculates Peak as 200% even though 8h/d is 100%. Why doe it do so?
Does this mean that Project thinks this way:
The duration of day 3 is 0.5d thus that day's Units (Peak) = Work / Duration = 4h / 05d = 100% in the first case and 8h/ 0.5d = 200% in the second?
Thank you,
Alex
Hi Alex,
I can't reproduce this behavior. Can you try on a blank new file? Also which Project version do you have? Is it upgraded up to the latest patch level?