MICROSOFT PROJECT [英] MICROSOFT PROJECT

查看:103
本文介绍了MICROSOFT PROJECT的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

关于特定任务,有哪些必要的调整使工作日成为非工作时间,周末成为工作时间?

解决方案

< blockquote>

IanABC,


假设更改仅适用于所选任务,则首先需要创建具有所需工作日和小时的自定义日历。创建完成后,您将使用该日历作为任务日历,可能需要也可能不需要为执行这些任务的任何资源制作基准日历的自定义
日历。


1。转到项目/属性组/更改工作时间


2。点击"创建新日历" "更改工作时间"窗口右上角的按钮


3。为您的新日历命名,然后点击"确定"


4。选择窗口下半部分例外列表上方的"工作周"选项卡,然后点击"详细信息"按钮。按钮


5。选择每一天,每次一个,并根据需要选择设置天数到这些特定工​​作时间,或者将天数设置为非工作时间


6。对于那些将是工作日的日子,如果需要,请输入From和To时间,包括任何休息时间(例如午餐,晚餐等)。


7。设置好所有日期后,点击"确定"。单击日历日时,您将看到工作时间。您可能希望点击工作日和周末,以确保它显示您的意图。


8。点击"确定"保存日历


9。在"甘特图"视图中插入"任务日历"字段。对于要跟踪自定义日历的每个任务,请选择该日历作为任务日历。任何具有"无"的任务在该字段中将遵循默认日历(即标准)


10。如果您还需要某些资源来处理自定义计划,请在资源表中选择该日历作为这些资源的基本日历


希望这会有所帮助。


约翰


In relation to a specific task, what are the necessary adjustments to make the weekdays to be the non - working time and the weekends to be the working time?

解决方案

IanABC,

Assuming the change will only apply to selected tasks, you first need to create a custom calendar with the desired work days and hours. Once that is created, you will then use that calendar as the Task Calendar and may or may not need to make that custom calendar the Base Calendar for any resources working those tasks.

1. Go to Project/Properties group/Change Working Time

2. Hit the "Create New Calendar" button in the upper right corner of the Change Working Time window

3. Give your new calendar a name and hit "OK"

4. Select the Work Weeks tab above the exceptions list in the lower part of the window and then hit the "Details" button

5. Select each day, one at a time, and either check the Set days to these specific working times, or Set days to nonworking time as desired

6. For those days that will be working days, enter the From and To times, including any break periods (e.g. lunch, dinner, etc.) if desired.

7. Once you have set up all days hit "OK". You will see the working times appear when you click on a calendar day. You might want to click on a weekday and weekend day to make sure it shows your intent.

8. Hit "OK" to save your calendar

9. Insert the Task Calendar field in the Gantt Chart view. For each task that you want to follow the custom calendar, select that calendar as the task calendar. Any task with a "none" in that field will follow the default calendar (i.e. Standard)

10. If you need certain resources to also work on the custom schedule, select that calendar as the Base Calendar in the Resource Sheet for those resources

Hope this helps.