自定义资源成本不会保存在项目中 [英] Custom Resource Cost Will Not Save in Project

查看:78
本文介绍了自定义资源成本不会保存在项目中的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

Hello Forum,

Hello Forum,

我们正在使用Project Server 2010. 我们为资源设置了默认费率。  但是,这些费率可能会根据合同谈判而改变。  在新项目中,我们正在尝试更改资源的成本以反映合同规定的
金额。  在资源工作表视图中,我们双击资源,然后获取资源信息窗口。  我们转到"成本"选项卡,选择生效日期(项目开始),将标准和加班费率更改为新签约的
值,单击确定以保存/关闭窗口。  然后,我们保存整个项目(等待"保存已完成"消息),然后发布整个项目(等待"发布已完成"消息)。  新的费率在项目中保持并显示
。  

We are working in Project Server 2010.  We have default rates set for our Resources.  However, these rates can change depending on contract negotiations.  On a new project, we are trying to change a Resource's cost to reflect the contracted amount.  In the Resource Sheet View, we double-click on the Resource, and get the Resource Information window.  We go to the Costs tab, select the Effective date (start of the project), change the Standard and Overtime Rates to the new contracted value, click OK to save/close the window.  Then, we Save the entire project (waiting for the "Save Completed" message), and Publish the entire project (waiting for the "Publish Completed" message).  The new rates hold and show up in the project.  

当我们关闭项目时,我们会收到确认是否要保存或放弃更改并签入项目的消息。  我们放弃它们(因为我们已经保存/发布了新的费率)。  当我们重新打开项目时,新的合同规定费率
消失了,费率又恢复到默认值。  当我们收到确认是否要保存/放弃更改的消息时,我们已尝试重新保存并重新发布。  不起作用。  我们如何对资源的
项目进行永久成本费率变更?

When we close the project, we get the message confirming if we want to Save or Discard Changes and Check-In the project.  We Discard them (because we already saved/published the new rates).  When we re-open the project, the new contracted rates are gone, and the rates have reverted back to the default values.  We've tried re-saving and re-publishing when we get the message confirming if we want to Save/Discard Changes.  Doesn't work.  How do we make permanent cost rate changes on a project for a Resource?

Julie

推荐答案

这就是Project Server的功能。所有企业资源都由Project Server Admin设置成本,并应用于Project Server中的所有项目。每次从Project Server打开项目时,资源费率,日历和所有其他Enterprise对象
(例如视图)都将恢复为默认设置。通常这很好,但在你的情况下却不是。每个项目的费率都要求多次,但到目前为止,没有运气。

This is what Project Server does. All Enterprise Resources have costs set by Project Server Admin and apply to all projects in Project Server. Every time you open a project from Project Server, the Resource rates, calendars and all other Enterprise objects such as views revert to default settings. Usually this is good, but in your scenario it isn't. Rates for each project is something requested many times, but so far, no luck.

所以你的解决方法是:

1)你可以使用费率B表示费率,并适用于所有作业的成本费率表B.但是,此解决方案仅允许5个不同项目的5种不同费率,因为只有5个(A-E)成本费率表。

1) You can use rate B for the rates and apply Cost rate Table B for all assignments. However this solution only allows 5 different rates for 5 different projects as there are only 5 (A-E) cost rate tables.

2)使用本地资源。这些不是由Project Server维护的。但是,您现在无法查看所有项目中资源的工作量,但您仍然可以按技能获得摘要。

2) Use local resources. These aren't maintained by Project Server. However you now can't look at the work loads of the resources across all projects, though you can still get a summary by skill.


这篇关于自定义资源成本不会保存在项目中的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!