问题描述

连接到项目服务器时加载摘要资源分配是否只拍摄分配数据的快照?如果另一个人之后发布他们的计划会发生什么,他们的资源工作量会在我打开的Project Professional状态下刷新吗?

Does Loading Summary Resource Assignments when connecting to project server only take a snapshot of the assignment data? What happens if another person publishes their plan afterwards, will their resource workload refresh in my opened state of Project Professional?

谢谢

Steve

推荐答案

史蒂夫 -

Steve --

我相信它是其他项目中任务数据的快照您打开企业项目的那一刻。要刷新其他项目的分配数据,我相信您需要关闭并重新打开您的项目。 如果我错了,我会很高兴有人纠正我。 希望这会有所帮助。

I believe it is a snapshot of the assignment data in other projects as of the moment you open your enterprise project. To refresh the assignment data from other projects, I believe you would need to close and reopen your project.  If I am wrong, I would happy for someone to correct me.  Hope this helps.