当所有资源都可用时,如何强制ms-project重新安排? [英] How to force ms-project to reschedule when all resources are available?

查看:150
本文介绍了当所有资源都可用时,如何强制ms-project重新安排?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我正在尝试使用2个资源在ms-project中设置会议:Alice和Bob


Alice的日历基于标准日历(每个工作日工作)和Bob的日历基于基于日历(每个工作日除星期二外工作):


默认情况下,ms-project设置任务到"固定单位"。



  • 当我将任务分配给Alice时,会议安排在星期二 - > ; ok
  • 当我将任务分配给Bob时,会议安排在星期三 - >好的


  • 我将任务分配给他们两个,持续时间变为2天,工作保持在16小时,但任务在周二和周三扩展 - >不行




  • 当我将任务更改为固定的持续时间时,ms-project会抱怨Alice被分配为200%而Bob被分配为0%......



如何将项目设置为:



  • 保持持续时间为1d?
  • 将工作保持在16小时?
  • 让ms-project将任务重新安排到第一个公共可用日期(即星期三)自动?

提前感谢您的帮助!

解决方案

Jaepetto,


首先,对于迟到的回复感到抱歉。该论坛有几天出现问题,其中没有出现新职位。问题现已解决。


如果没有关于Alice和Bob可能被分配到的其他任务的更多信息,我只能假设Alice已经在周三100%分配给另一个任务,这就是为什么你获得了整体分配。你使用资源调配吗?这可能是"强迫"的唯一
方式。项目安排会议时两个资源都可用,并且可用我的意思是两个资源都在工作而不是关闭。


John




I'm currently trying to setup a meeting in ms-project with 2 resources: Alice and Bob

Alice's calendar is based on the standard calendar (working every weekday) and Bob's calendar is based on the based calendar (working every weekday except on Tuesdays):

By default, ms-project sets the tasks to "Fixed Units".

  • When I assign the task to Alice only, the meeting is scheduled for Tuesday -> ok
  • When I assign the task to Bob only, the meeting is scheduled for Wednesday -> ok
  • When I assign the task to the both of them, the duration changes to 2 days, the work remains at 16 Hrs but the task expands over Tuesday and Wednesday -> Not OK

  • When I change the task to a fixed duration, ms-project complains that Alice is allocated at 200% and Bob at 0%...

How can I set project up to:

  • keep the duration to 1d?
  • keep the work to 16 hrs?
  • have ms-project reschedule the task to the first common available day (i.e. Wednesday) automatically?

Thanks in advance for your help!

解决方案

Jaepetto,

First, sorry for the late response. The forum had problems for several days wherein new posts were not appearing. The issue is now fixed.

Without more information about other tasks Alice and Bob may be assigned to, I can only assume that Alice is already allocated 100% to another task on Wednesday and that's why you get the overallocation. Did you use resource leveling? That may be the only way to "force" Project to schedule the meeting when both resources are available and by available I mean both resources are at work and not off.

John