为什么我的燃尽图不会显示sprint未来的工作? [英] Why won't my burndown chart show future work for the sprint?

查看:94
本文介绍了为什么我的燃尽图不会显示sprint未来的工作?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我已经设置了一个测试项目,设置冲刺日期,团队容量设置,设置积压项目和相关任务以及剩余时间(我甚至说过工作类型以防万一)。当我进入刻录图表时,它显示了可用容量和理想趋势的
线,但剩余工作的蓝色块仅达到"今天的日期"。线和我无法解决为什么,它让我疯了!我在星期五设置这个,所以在周末等了两天,看看
延迟的时间是否有所作为 - 事实并非如此。我使用了scrum项目模板并选择了"团队基础版本控制"。

Hi, I have set up a test project, set sprint dates, team capacity set, set backlog items with associated tasks with remaining time on them (I have even said the type of work in case that makes a difference). When I go into the burn down chart it shows a line for available capacity and ideal trend but the blue block of remaining work is only up to the "today's date" line and I can't work out why and it's driving me crazy! I set this up on Friday so waited two days over the weekend to see if the time delay makes a difference - it didn't. I used a scrum project template and selected "team foundation version control".

请问任何想法?

非常感谢

Judith

推荐答案

嗨Judith,

Hi Judith,

Sprint的Burndown图表是确定您的团队是否有望完成其冲刺计划。欲了解更多信息,请参阅以下链接:

The Burndown chart for Sprint is to determine if your team is on track to complete its sprint plan. For more information, please refer to the link below:

https://www.visualstudio.com/en-us/docs/work/scrum/sprint-burndown  

剩下的工作仅限于"今天的日期"线是设计的,Burndown无法预测未来的工作。

The remaining work is only up to the "today's date" line is by design, Burndown could not forecast future work.

要查看sprint的工作进度,请使用Sprint Planning功能:

To see your work progress of a sprint, please use Sprint Planning feature:

https://www.visualstudio.com/en-us/docs/work/scrum/ sprint-planning

最好的问候


这篇关于为什么我的燃尽图不会显示sprint未来的工作?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!