在任务使用中显示数字字段 [英] Showing a Number Field in the Task Usage
问题描述
大家好,
我正在尝试使用MS Project在任务使用情况显示中产生现金流,这是我已经实现的。
然而,此外,我想为某些任务指定一个数字,这些任务代表我可以向他们索取的碳单位。
我希望包含这个数字关于任务使用情况,显示我不仅可以显示现金流量,还可以显示合约期限内每月的碳排放量。
任何人都可以帮忙吗?我正在使用Project 2013
非常感谢。
Tim
< blockquote>
嗨Tim,
如何使用碳材料资源,标签为"单位"。因此,将此资源分配给具有特定单元的任务,并将任务使用视图与资源图(累积工作)结合使用。可能是这样:
Hi all,
I am trying to use MS Project to produce a cash flow, within the Task Usage display, this I have achieved.
However in addition, I would like to assign a number to certain tasks which represents a unit of carbon I can claim against them.
I would like this number to be included on the task usage, show I can not only show cash flow, but when carbon will be delivered over the life of the contract, month on month.
Can anyone help please? I am using Project 2013
Many thanks.
Tim
Hi Tim,
What about using a material resource for carbon, the label being "units". Thus assign this resource to task with a certain unit and use the task usage view combined with the resource graph (cumulative work). Here is what it could be: