每次更新项目时任务分裂...... [英] Tasks splitting each time I update the project...

查看:53
本文介绍了每次更新项目时任务分裂......的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

大家好

问题:每当我对我的程序进行状态调整时,任何不完整的任务都会在使用更新程序功能时中断/分裂(我倾向于每月1-2次对所有任务进行状态,然后使用更新功能并告诉MSP在我的状态之后的第二天运行剩余任务持续时间的
余额。结果,我在gant图表中得到一个任务栏,它被拆分为"块"。

The issue: whenever I status my programmes, any task that is incomplete and has a remaining duration breaks / splits when using the update programme function (I tend to status all tasks 1-2 times a month, then use update function and tell MSP to run the balance of remaining task durations from the day after my status). As a result I get a task bar in the gant chart that is split into 'chunks'.

我真的不喜欢这样显示的任务....有什么方法可以阻止这个吗?

I really dislike the tasks displaying like this....is there any way to stop this?

一般来说,我更确切地说,任务显示为从实际开始到实际结束的完整块(或者如果不完整,则实际开始到今天+剩余持续时间)。

Generally speaking, I would much rather tasks show as an unbroken block from Actual Start to Actual a Finish (or if incomplete, then actual start to today + remaining duration).

我被告知P6中不存在此问题,但我们不使用Pirmavera产品。

I have been told that this problem does not exist in P6, but we don't use Pirmavera products.

有人可以帮忙吗?

谢谢,罗伯特




推荐答案

嗨罗伯特,

可能有很多原因,我需要查看实际项目并检查选项以解决此问题,以告诉您发生这种情况的原因。 你能分享一下这个计划吗?

There could be many reasons, and I would need to see the actual project and check the options to troubleshoot this to tell you why this is happening.  Can you share the plan?


这篇关于每次更新项目时任务分裂......的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文