将Project Server 2007从SQL Server 2005迁移到SQL Server 2008的步骤? [英] Steps to migrate Project Server 2007 from SQL Server 2005 to SQL Server 2008?

查看:64
本文介绍了将Project Server 2007从SQL Server 2005迁移到SQL Server 2008的步骤?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我们需要将Project Server 2007从SQL Server 2005迁移到SQL Server 2008.



1。它是否像备份和恢复数据库以及将Project Server指向新的数据库服务器一样简单?或者应该遵循一些具体步骤?



2。
http://technet.microsoft.com/en-us上的文章/library/dd207290(off.12).aspx
 是关于将数据库从一个数据库服务器移动到另一个数据库服务器(相同版本)。在一个地方,它提到
备份所有数据库 ,但在另一个地方它提到
< span style ="display:inline!important; float:none; word-spacing:0px; font:13px / 18px'Segoe UI','Lucida Grande',Verdana,Arial,Helvetica,sans-serif; text-transform:none ;颜色:#2a2a2a; text-indent:0px; white-space:normal; letter-spacing:normal; text-decoration:underline; orphans:auto; widows:auto">
你应该只回来从源数据库服务器获取Draft和Published数据库
从2005年到2008年应该怎么办?



问候,


Amit
Gupta






$

解决方案

嗨Amit,


这很简单,就像进行备份和恢复一样。 


您必须在新的sql server 2008服务器中恢复草稿,发布,存档,报告和内容数据库,然后将项目服务器指向新数据库。


请忽略该行


We need to migrate Project server 2007 from SQL Server 2005 to SQL Server 2008.

1. Is it as simple as doing backup and restore of databases and pointing Project Server to the new DB server? Or there are some specific steps that should be followed?

2. Article at http://technet.microsoft.com/en-us/library/dd207290(office.12).aspx is about moving databases from one DB server to another (same versions). At one place, it mentions to backup all databases but at another place it mentions that You should only back up the Draft and Published databases from the source database server. What should be done when moving from 2005 to 2008?

Regards,

Amit Gupta

解决方案

Hi Amit,

It is simple as doing backup and restore. 

You have to restore draft, publish, archive, reporting and content DB in new sql server 2008 server then point project server to new DB.

Please ignore that line .


这篇关于将Project Server 2007从SQL Server 2005迁移到SQL Server 2008的步骤?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!