问题描述

大家好,


我有几个问题。


1。是否有可能以某种方式将内部企业共享点日历​​与PWA中的日历链接?

2.如果没有,您如何在每个员工(假期,病假)中显示PWA企业日历(假期)和资源日历离开)。$
3.我计划创建行政任务(休假,培训,商务旅行,生病),以便每位员工可以报告他是否生病,受过训练或正在度假。我不知道多少是正确的。

目标 - 考虑图表上的资源可用性,例如培训,旅行等。

经理,如果他向一名员工指定了一份任务令,例如在医院,只是看到了它并将其重新分配给另一名员工。

解决方案

#1 - 不,据我所知,开箱即用功能不可行。


#2 - 企业日历无法显示因为它以不可访问的二进制格式存储。如果您使用的是"管理时间类别",则可以使用"资源日历"。管理员时间在RDB中可用,因此当人们不在这里时,您可以显示例外
,假设他们正在进入计划中断。


#3 - 只有3管理员时间的核心方案。虽然您可以创建n个变体,但这些只是所需的3个桶。



  • 我过去不在这里,需要记录下来。 (即生病)
  • 我在这里但不能参与项目工作(支持)
  • 我将来不会在这里(假期)

虽然你可以添加多个类别,但我不会过分,除非你有一个驾驶业务需要跟踪在分区会议上花了多少小时等等。每一行增加了每周的决定和每个用户的入场时间都要谨慎添加。


Treb Gatte @tgatte




Hi all,

I have several questions.

1. Is it possible to somehow link the internal corporate sharepoint calendars with calendars in PWA?
2. If not, how you can display in PWA enterprise calendar (holidays) and resource calendar for each employee (vacation, sick leave).
3. I  plan to create administrative tasks (vacation, training, business trip, sick), so that each employee can report back if he was ill, trained or was on vacation. I do not know how much it will be correct.
The goal - is to take into account resource availability on the chart, such training, travel, etc.
The manager, if he appointed a task order to an employee who, for example, at the hospital, just saw it and reassign it to another.

解决方案

#1 - No, this is not possible as far as I know with out of box functionality.

#2 - The enterprise calendar cannot be displayed since it is stored in a binary format that is inaccessible. The Resource Calendar can be, sort of, if you are using Administrative Time Categories. The Admin time is available in the RDB so you can show exceptions of when people aren't here, assuming they are entering planned outages.

#3 - There are only 3 core scenarios for Admin time. While you can create n variations, these are really the only 3 buckets needed.

  • I wasn't here in the past and need to record this. (i.e. Sick)
  • I am here but can't work on Project work (Support)
  • I won't be here in the future (Vacation)

While you can add as many categories, I wouldn't go overboard unless you have a driving business need to track how many hours are spent in divisional meetings, etc. Each line added adds weekly decision and entry time for every user so add with care.