摘要任务持续时间 - 人日? [英] Summary Task Duration - Man Days?

查看:191
本文介绍了摘要任务持续时间 - 人日?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

嘿伙计们,


我对Project很新,所以请耐心等待!我会尽量做到尽可能完整!


刚刚迷惑自己并尝试了一些示例项目我已经确定总结任务顶部的持续时间实际上是多久这项任务将从头到尾进行,而不是像我之前想到的那样,分配给每个
任务的人日总和。


从概念上讲,这看起来很奇怪说三个任务需要2天,15天和4天,增加21天以外的东西。我在实践和测试中有过一些场合,总结任务的持续时间多于和少于这个总和。


是否可以添加一个工时/天等总结除了或者不是持续时间?它似乎也避免了混淆,如果没有将任务模式更改为手动,就无法删除此摘要持续时间,这似乎不太理想。


任何指针都非常赞赏,我想当我们'所有精通Excel的人只是看起来很奇怪(但有点意义!!)



谢谢:)

解决方案

你好Rob-R


欢迎来到项目 - 这是你需要做的第一件事之一周围是工作和持续时间之间的差异。 如果您插入工作栏,您会看到可以在那里输入值(默认为小时,但您可以在
选项中更改)。 就个人而言,我不会更改摘要任务上的任何值,我会将它们保留为AutoScheduled并让他们以摘要任务完成工作。


那里有很多好的书籍和视频以及其他资源 - 显然我会指引你到我的,这是针对新手的;)


http://shop.oreilly.com/product/0790145369154.do


BR, 本。


Hey guys,

I'm pretty new to Project so bear with me! I'll try to be as complete as possible!

Having just confused myself and tried a few sample projects I've ascertained that the duration at the top of a summary task is actually how long this task will take from start to finish, not, as I'd previously thought, a sum of the man days assigned to each task.

Conceptually it looks odd to have say three tasks taking 2 days, 15 days and 4 days adding to something other than 21 days. I've had occasions in practice and test where the summary task duration is both more and less than this sum.

Is it possible to add a man hours/days etc summary either in addition to or instead of the duration? It also seems to avoid confusion one can't remove this summary duration without it changing the task mode to manual, which seems less than ideal.

Any pointers much appreciated, I guess when we're all well versed with Excel this just looks plain odd (yet sort of makes sense!!)

Thanks :)

解决方案

Hi Rob-R

Welcome to Project - and one of the 1st things you need to get your head around is the difference between work and duration.  If you insert the work column, you see you can enter the values in there (by default in hours, but you can change that in the options).  Personally I wouldn't change any values on Summary Tasks, I would leave them as AutoScheduled and let them do their jobs as Summary Tasks.

There are lots of good books and videos and other resources out there - obviously I'll direct you to mine which is aimed at newbies ;)

http://shop.oreilly.com/product/0790145369154.do

BR,  Ben.


这篇关于摘要任务持续时间 - 人日?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!