Auto正在创建任务,以便在下午5点结束时开始...... [英] Auto is creating tasks to start at the end of the day 5 PM...

查看:73
本文介绍了Auto正在创建任务,以便在下午5点结束时开始......的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我正在为客户使用项目2010标准,并注意到当我创建具有前任的任务时,任务开始时间是下午5点。 我更喜欢让任务从上午9点开始。 这个配置在哪里管理?我已经检查了"选项"
" schedule"。 我有一个7小时工作日和一周35小时但仍然无法在一天开始创建任务。 当我手动强制开始日期然后创建一个约束,然后当发生更改时,它们不会自动更新,就像"前任可以尽快"的约束一样。 我更喜欢没有约束,并且"尽快"使用"所有任务。

I am using project 2010 standard for a client and noticed that when I create tasks that have predecessor the task start time is 5 PM.  I prefer to have the tasks start at 9 AM.  Where is this configuration managed? I already checked "options" "schedule".  I have a 7 hour work day and 35 hours a week but still cannot get tasks to be created at the beginning of the day.  When I manually force the start date then a constraint is created and then when changes occur they are not automatically updated like a constraint of 'as soon as possible with predecessors would do.  I prefer to have no constraints and use "as soon as possible" for all the tasks.

有关如何解决此问题的任何见解表示赞赏:)

Any insight on how to fix this issue is appreciated :)

谢谢,

Dora

推荐答案

看起来您可能与默认日历发生冲突。  尝试在Project>中更新日历更改工作时间以反映7小时工作日。 
Looks like you may be running into a conflict with the default calendar.  Try to update the calendar in Project > Change working time to reflect 7 hour work days. 


这篇关于Auto正在创建任务,以便在下午5点结束时开始......的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!