问题描述
管理层希望看到整数,而不是3.64或2.89天。有没有办法好好改变它?
Management wants to see round numbers, not 3.64 or 2.89 days. Is there a way to change this for good?
推荐答案
嗨Riollano -
Hi Riollano --
如果您的任务持续时间显示为分数/小数,那么您的项目和任务日历可能与项目的日历选项不匹配。
If your task durations are appearing as fractions / decimals, then perhaps your project and task calendars do not match the calendar options for the projects.
检查项目日历的工作时间并将它们与项目的日历选项,例如默认开始时间和默认结束时间:
Check the working hours for your project calendar and compare them to the calendar options for the project, such as default start time and default end time:
- 项目/任务日历工作时间:'项目'选项卡> "更改工作时间"
- 项目日历选项:"文件"标签> '选项'> 'Schedule'
这些说明假设您使用的是Project 2010;如果你使用的是不同版本的MS Project,那么这个过程可能会略有不同。
These instructions assume that you are using Project 2010; if you are using a different version of MS Project, then the process may be slightly different.
祝你好运!
- tz