是否有可能在没有基线的情况下重新选择落后于计划的任务? [英] Is it possible to refelect a task to be behind schedule without a baseline?
问题描述
有一些程序可以与MS Project一起使用,它可以将任务标记为"落后于计划"而没有基线。怎么可能呢?
There a few programs out there, that works with MS Project, that label tasks as "behind schedule" without a baseline. How can that be possible?
推荐答案
Riollano -
Riollano --
在微软项目中,迟到任务是时间分段%完成不会转到当前日期行或状态日期行的任何任务。 例如,假设您有一个持续时间为10天的任务。 该任务应该在星期一
开始,并在任务的第二周在星期五结束。 在第一周结束的星期五,这个为期10天的任务应该具有50%的完成百分比值。 但如果任务的完成百分比值小于50%,则表示该任务是延迟任务。
In Microsoft Project, a Late Task is any task whose timephased % Complete does not go to the Current Date line or the Status Date line. For example, suppose you have a task with a Duration of 10 days. The task is supposed to start on a Monday and finish on a Friday in the second week of the task. On Friday at the end of the first week, this 10-day task should have a % Complete value of 50%. But if the task has a % Complete value less than 50%, this means the task is a Late Task.
说实话,为了真正有效地跟踪项目差异,每个项目经理都需要在他/她开始跟踪实际进度之前,在他/她的项目中保存基线。 希望这会有所帮助。
Truthfully, to be really effective in tracking project variance, every project manager needs to save a Baseline in his/her projects before he/she begins tracking actual progress. Hope this helps.