时间表 [英] Timesheet
问题描述
在EPM 2010中,当资源在时间表中输入的实际小时数多于计划小时数时小时数更新为等于实际小时数。知道为什么会发生这种情况以及如何防止计划时间仍然显示为时间表中的原始
计划小时数,但是时间表和计划中的实际小时数会更新以显示实际小时数?
In EPM 2010, when a resource enters more actual hours in his timesheet than planned hours, the planned hours are updated to equal the actual hours. Any idea why this happens and how it can be prevented so that the planned hours still display as the original planned hours in the timesheet, but the actual hours in the timesheet and the plan is updated to display the actual hours?
例如。乔治被分配了4个小时的任务,但在他的时间表中工作并记录了6个实际小时,并将其提交给他的经理批准。他在计划表中计划的小时数会自动更新为显示6而不是4,原计划为
。
E.g. George was allocated 4 hours on a task, but worked and recorded 6 actual hours in his timesheet and submitted this to his manager for approval. His planned hours in his timesheet are automatically updated to display 6 instead of 4 as was originally planned.
请详细说明为何会发生这种情况以及如何防止这种情况发生。
Please shed some light on why this happens and how it can be prevented.
谢谢,
Jaco
推荐答案
你好Jaco
Hi Jaco
"计划"和"计划"值将随实际值而变化。
这就是项目的工作方式,这用于重新计算项目中的日期/持续时间/工作。
如果您需要与计划的工作或日期进行比较,您需要用于将初始值保存为基线。然后你将有一个快照供比较。
The "planned" values will change with actuals.
That's how project works, and this is used for recalculate the dates/durations/work in your project.
If you need comparison with your planned work or dates, you need to use to save your initial values as a baseline. Then you will have a snapshot for comparing.
Tomas