我创建了一个包含14个任务的项目,所有这些任务都是链接和自动安排的。 我还创建了一个摘要任务,用于将任务分组到一个阶段,并且还显示总持续时间。 该项目还使用
标准日历安排。 我想通过创建一个包含6天工作周的新日历来试验加速计划。 每天10小时。 当我将日历应用于现有计划时,摘要任务的持续时间不会更改。 
为什么这是显示加速计划的最佳方式?

I have created a project with 14 tasks all of which are linked and auto scheduled.  I also created a summary task for the pupose of grouping the tasks in a phase and also for it to show total duration.  The project was also scheduled using the standard calendar.  I wanted to experiment with an accelerated schedule by creating a new calendar with 6 day work weeks  an 10 hours per day.  When I applied the calendar to my existing schedule, the duration on the summary task did not change.  Why is that and what is the best way to show an accelerated schedule?

推荐答案

OTC老师,

OTC Teacher,

嗯,你确实得到了加快的时间表。看看完成日期。

Well, you did get an accelerated schedule. Take a look at the finish date.

请记住,持续时间字段是开始和结束之间工作时间的差异。通过将星期六或星期日作为工作日,您将创建一个额外的工作日,因此6天任务仍然是6天任务,它只是提前一天结束。

Remember that the Duration field is the difference in working time between the start and finish. By making Saturday or Sunday a working day you are creating an extra working day so a 6 day task is still a 6 day task, it just finishes a day earlier.

至于10  小时工作日,可能会也可能不会缩短时间表。如果您定义"天",作为10小时而不是默认的8小时,您将看到持续时间字段中的差异,但是每天10小时不会缩短计划的
(即更改完成日期)。一天10小时的工作真正重新定义了一天中有多少小时。例如,5天任务(使用默认的每天8小时设置)现在将在"持续时间"字段中显示为4天。 40小时是
仍然是40个小时。

As far as the 10  hour day goes, that may or may not contribute to shortening the schedule. If you define a "day" as 10 hours instead of the default 8 hours your WILL see a difference in the Duration field, but a 10 hour day by itself will not shorten the schedule (i.e. change the finish date). All a 10 hour day will really do is redefine how many hours there are in a day. For example a 5 day task (using the default 8 hours per day setting) will now display as 4 days in the Duration field. Forty hours is still forty hours.

希望这会有所帮助。

John