问题描述

我想知道是否有办法将资源池管理到不同的组中。这是因为,当我稍后创建不同的资源计划时,我不必将每个资源添加到每个活动,而是将整个组(包括40个资源)
一次添加到一个活动。 

I wonder if there is a way to manage your resource pool in to different groups. This because, when I later create different Resource Plans I don't have to add each resource to each activity, instead I add the entire group (including lets say 40 resources) to one activity at a time. 

我们现在有一个包含大约1800个资源的资源池......所以为这些资源实现某种系统会很棒。

We now have a resource pool containing around 1800 resources... So it would be great to implement some kind of system for these resources.

是有什么方法可以做到,或者我是否必须一次添加一个资源?

Is there any way this can be done, or do I have to add one resource at a time?

/ Chip

推荐答案

Hi Chip,



我相信你可以使用  Project Server 2010中的团队分配。

http://projectserverblogs.com/?p= 375

http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/0890e9ab-e1ac-438b-b5dc-b22dd3162e2a/


Hi Chip,

I believe that you can use  team assignments in Project server 2010.
http://projectserverblogs.com/?p=375
http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/0890e9ab-e1ac-438b-b5dc-b22dd3162e2a/