如何阻止过去的资源分配从资源表中显示出来? [英] How do you stop resource overallocations from the past from showing up in the resource sheet?

查看:90
本文介绍了如何阻止过去的资源分配从资源表中显示出来?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

亲爱的,

如何阻止过去的资源分配从资源表中显示出来?所以,基本上我想找到一种方法,这样只有我将要计划的任务才会被考虑在资源的过度分配中(或者给我一个过度分配警告)。

How do you stop resource overallocations from the past from showing up in the resource sheet? So, basically I want to find a way, so that only the tasks I will be planning are considered in the overallocation of resources (or give me an overallocation warning).

显然,删除已完成的任务(在我当前日期之前已过度分配)将是一个解决方案,可以删除即将发布的过度分配警告。但是我需要保留旧任务及其持续时间的存档,以便保持项目的概览和历史记录

Obviously deleting the completed tasks, which were overallocated before my current date, would be a solution to remove the overallocation warning coming up. But I need to keep an archive of old tasks and their duration, so as to keep the overview and history of the project.

感谢您的帮助。

问候,

Stef

Stef

推荐答案

如果任务是过去的话,将它们设置为100%完成(或者如果它们未完成则将来重新编程)。

If the tasks are in the past, set them to 100% complete (or reshedule them in the future if they are not complete).

希望这个帮助。


这篇关于如何阻止过去的资源分配从资源表中显示出来?的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文
登录 关闭
扫码关注1秒登录
发送“验证码”获取 | 15天全站免登陆