问题描述

如果我的项目已部分完成,我想移交给项目经理(PM)...意味着存在一些小问题,我没有时间解决,我想移交给PM,以便他可以将其发送给专家..so,所以任何人都可以告诉我将该问题交给PM的标准格式.

If My project is partially done and i want to handover to project manager(PM)...means there are some minor issue and i dont have time to solved and i want to handover to PM so he can send that to expert..so any one can tell me the standard format to give that problem to PM..

推荐答案

项目交接没有标准格式IMO.这取决于公司的标准,您已签订的合同(如果您已签订合同)等.但是,根据我工作过的以前的公司,在他们的流程上有一些类似的步骤.您可能要:

1.通知项目经理将移交项目.这可能包括移交应用程序,包括必要的设计文件.
2.不管项目是否有问题,项目经理或将要交给项目的人都必须提供签字,即他们已经了解该项目,他们已经熟悉了该应用程序的技术细节. ,并且他们同意轮到该对系统进行维护/增强了.

最好查看您的合同,或询问项目经理如何处理这种情况.
There''s no standard format for project handover, IMO. This depends on the standards of the company, the contract you have signed(if you signed one), etc. However, based on the previous companies I worked for, there are some similar steps on their processes. You may want to:

1. Inform the PM that the project will be handed over. This may include handing over the application, including necessary design documents.
2. Regardless of whether the project has issues or not, the PM, or whoever the project will be handed to, will need to provide signoff, meaning, that they already understand the project, they already familiarized themselves on the technical details of the application, and they agree that its their turn to do maintenance/enhancement to the system.

Better review your contract, or ask the PM on how to handle this kind of scenario.